With its most recent delivery of F-35 CTOL center fuselage AF-14 (right), Northrop Grumman has moved to a ten day production/delivery interval.

Northrop Grumman delivering success in transition to F-35 full rate production

If you want to gauge Northrop Grumman Corporation's (NYSE:NOC) commitment to help the F-35 Joint Strike Fighter program make a successful transition to full rate production, just look at the calendar.

As recently as two years ago, the company, a principal and founding member of the Lockheed Martin-led F-35 industry team, was delivering a center fuselage for this fifth generation, multi-role fighter to Lockheed Martin's final assembly facility in Fort Worth, Texas about once every 30 days. With this week's delivery of the center fuselage for the F-35 designated AF-14, however, that delivery interval has now dropped to just 10 days. And by early next year, the number is expected to drop to eight days.

"We're moving steadily down the production learning curve, streamlining our processes and increasing our workforce as we continue to transition from delivering approximately two center fuselages per month to an eventual rate of delivering one center fuselage per day," said Mark Tucker, vice president and F-35 program manager for Northrop Grumman's Aerospace Systems sector.

Northrop Grumman is responsible for the production of all center fuselages for all three variants of the F-35: conventional takeoff and landing (CTOL); short takeoff, vertical landing (STOVL); and the carrier variant. All F-35 center fuselages are currently being assembled in the company's Palmdale Manufacturing Center

According to Mike Jones, director of F-35 production operations for Northrop Grumman Aerospace Systems, the steady drop in production interval – the time between center fuselage starts, or between center fuselage deliveries – can be attributed to the company's larger and increasingly skilled F-35 workforce, and to its more efficient utilization of center fuselage production tools.

"For the past year, we've been on a pretty consistent 12-day production interval cycle," said Jones. "Over the last month or so, during the latter phases of assembling the center fuselage for BF-12, an F-35B STOVL aircraft, however, we've transitioned to a 10 day production interval cycle to support Lockheed Martin's updated final assembly schedule. The delivery of AF-14 is the first center fuselage to reflect that new, lower production interval."

The shrinking delivery interval has also been aided by the fact that Northrop Grumman's F-35 touch-labor force has grown from about 65 employees two years ago to more than 250 employees today, added Jones. That work force is expected to reach 300 by the end of the year.

Over the longer term, Northrop Grumman plans to reach the full production rate of completing approximately one center fuselage per day using a new integrated assembly line (IAL) currently being installed at its Palmdale Manufacturing Center. Expected to begin operations in early 2011, the IAL will feature automated guided vehicles that will simplify the process currently used to move center fuselage structures from one assembly station to the next. It is expected to help reduce F-35 program costs, and improve the precision and overall quality of the center fuselage production process.

In addition to producing the F-35 center fuselage, Northrop Grumman also designed and produces the aircraft's radar and other key avionics including electro-optical and communications subsystems; develops mission systems and mission-planning software; leads the team's development of pilot and maintenance training system courseware; and manages the team's use, support and maintenance of low-observable technologies.

Press release issued by Northrop Grumman Aerospace Systems on August 9, 2010


 Contact details from our directory:
Northrop Grumman Aerospace Systems Airframer
Lockheed Martin Aeronautics Company Airframer


 Related aircraft programs:
Lockheed Martin F-35 Lightning II


 Related directory sectors:
Airframe Assemblies

Enhanced listings:

Victrex Plc
New VICTREX® AE250 composites and hybrid molding technology are changing the equation in Aerospace composites – find out more!

United Performance Metals
A global distributor and processor of titanium products for over 40 years, and a leading supplier to the aerospace industry

USA Borescopes
USA Borescopes is a global supplier of world class visual inspection equipment. We are the one stop source for aviation professionals.

Samuel, Son & Co.
Looking for a quality metals supplier? Samuel can provide Aircraft Quality metals that meet Commercial and Military specifications

Dexmet Corporation
Dexmet MicroGrid® an innovative product line that help improve the composite aircraft withstand the rigors of a lightning strike

See our advertising tariff.


Monthly page limit exceeded. Please buy a subscription.

© Copyright of Airframer Limited, operated under licence by Stansted News Limited 2016. Terms & Conditions of reading.